Ocean City, NJ – The Cape May County Municipal Utilities Authority (CMCMUA) Bay Ave Force Main Rehabilitation Project will commence on Tuesday, September 3, 2019. 

Project Scope:

  • Replace 20in Ductile Iron Force Main with 20in PVC Force Main.
  • Slip Line existing 20in Ductile Iron Force Main with 16om HDPE
  • Extents: 31st and Haven to 8th and Bay

Scope and Timeline:

Bay_Avenue_Project_Scope.jpg
Active Work:
Lafayette Utility Company (Contractor) will be working mobilizing material and equipment (Pipe , Heavy Equipment, Traffic Control Equipment) in the vicinity of 31st and Haven Aves. It is not anticipated that physically work will begin until the week 9/9/19.  

Traffic:
Traffic Control Measure will be implemented and enforced upon the commencement of physical work on 9/9/19.

Contact Information:
Please refer all inquiries to bayaveforcemain@cmcmua.com
Phone Calls to Josh Palombo, Wastewater Program Manager, CMCMUA (609) 456-9026 