Wastewater Force Main Replacement Project Bay Avenue, Ocean City Update #12 - Week of 11/18/19 through 11/22/19

Cape May County Municipal Utilities Authority

Wastewater Force Main Replacement Project

Bay Ave, Ocean City, NJ

Update #12 - Week 11/18/19 through 11/22/19

Active work:

As of the end of the day (Friday 11/15/19), the Contractor will have installed PVC piping, backfilled, and temporary paved up to 27th Street.

On Monday, 11/18/19, the crew that is at 27th Street will proceed northward to work between 27th and 26th Streets. Sometime between Monday, 11/18/19,  and Thursday, 11/21/19, a second crew will be added to begin work at 14th Street and work southward. When that happens, Bay Ave will be closed between 14th and 34th Streets and a Police Traffic Director will be stationed at 14th Street. Until that happens, Bay Ave will be closed between 24th and 34th Streets.

Traffic:

Over the weekend (11/16 - 11/17) Bay Avenue will be open to two lanes of traffic with lane shifts around stored materials and equipment.

As mentioned above, Bay will be closed from 34th to 14th street upon the second crew commencing work. Prior to the second crew beginning work, Bay Ave will be closed from 34th to 24th. Traffic detours will be established to divert motorists to West Ave.

traffic week 4.png

Scope/Timeline:

timeline week 4.png

Contact Information:
Please refer all inquiries to bayaveforcemain@cmcmua.com
Phone Calls to Josh Palombo, Wastewater Program Manager, CMCMUA (609) 456-9026 