Wastewater Force Main Replacement Project Bay Avenue, Ocean City Update #13 - Week of 11/25/19 through 11/29/19

Cape May County Municipal Utilities Authority

Wastewater Force Main Replacement Project

Bay Ave, Ocean City, NJ

Update #13 - Week 11/25/19 through 11/29/19

Active work:

As of the end of the day (Friday 11/22/19), the Contractor will have installed PVC piping, backfilled, and temporary paved up to 26th Street. The contractor's North crew will have saw cut the pavement and staged material and equipment in the vicinity of 18th St to 15th St.

From Monday (11/25/19) to Wednesday (11/27/19) the South crew will be working between 26th and 25th Streets. The North crew will be working between 15th and 16th Streets. No work is scheduled to be done from Thanksgiving (11/28/19), through Sunday (12/1/19). 

Traffic:

Currently, Bay Ave is closed, with the exception of local traffic, from 34 St to 14th St.
Over the weekend (11/23 - 11/24) Bay Avenue will be open to two lanes of traffic with lane shifts around stored materials and equipment.

From Monday (11/25/19) to Wednesday (11/27/19) Bay will be closed from 34th to 14th street.  Traffic detours will be established to divert motorists to West Ave with a Police Traffic director stationed at 14th Street to assist in traffic control.

From Thanksgiving (11/28/19), through Sunday (12/1/19) Bay Avenue will be open to two lanes of traffic with lane shifts around stored materials and equipment.

traffic week 4.png

Scope/Timeline:

timeline week 4.png

Contact Information:
Please refer all inquiries to bayaveforcemain@cmcmua.com
Phone Calls to Josh Palombo, Wastewater Program Manager, CMCMUA (609) 456-9026 

For Prior Updates Click Here