Wastewater Force Main Replacement Project Bay Avenue, Ocean City Update #15 - Week of 12/9/19 through 12/13/19

Cape May County Municipal Utilities Authority

Wastewater Force Main Replacement Project

Bay Ave, Ocean City, NJ

Update #15 - Week 12/9/19 through 12/13/19

Active work:

As of the end of the day Friday (12/6/19), the Contractor’s North crew will have installed a new PVC pipe, backfilled and paved from 15th Street going South to a point about 150' North of 16th Street. The South crew will have done the same work going North to a point about 150' South of 25th Street.

From Monday (12/9/19) to Friday (12/13/19) the work will continue in the same direction for both crews. 

Traffic:

For the weekend (12/7/19 – 12/8/19), Bay Avenue will be open to two lanes of traffic with lane shifts around stored materials and equipment.

On Monday (12/9/19) Bay will again be closed from 34th to 14th streets.  Traffic detours will be established to divert motorists to West Ave with a Police Traffic director stationed at 14th Street to assist in traffic control. At some point within the next two weeks, the South Crew will proceed North of 24th street. Once this happens, the closure of Bay will be restricted between 24th and 14th Streets. 

traffic week 4.png

Scope/Timeline:

Timeline for Force Main Project

Contact Information:
Please refer all inquiries to bayaveforcemain@cmcmua.com
Phone Calls to Josh Palombo, Wastewater Program Manager, CMCMUA (609) 456-9026 

Prior Updates