Wastewater Force Main Replacement Project Bay Avenue, Ocean City Update #2 - Week of 9/9/19 through 9/13/19

Cape May County Municipal Utilities Authority

Wastewater Force Main Replacement Project

Bay Ave, Ocean City, NJ

Update #2 - Week 9/9/19 through 9/13/19

Active work:
During the week of 9/9 through 9/13, Lafayette Utility Company (Contractor) will continue to mobilize material and equipment (Pipe , Heavy Equipment, Traffic Control Equipment) in the vicinity of 31st and Haven Aves. The contractor will also begin sawcutting of pavements from 31st St up to 18th & Ba but will not begin trench excavation and pipe installation until the week of 9/16 to 9/20.

Traffic:
Traffic detours will not be required during the saw cutting operation. Traffic protection will be provided by flag-persons. 

Scope/Timeline:

timeline week 2.png

Contact Information:
Please refer all inquiries to bayaveforcemain@cmcmua.com
Phone Calls to Josh Palombo, Wastewater Program Manager, CMCMUA (609) 456-9026 

For Prior Updates Click Here