Active work:
Beginning Monday, 9/16/19 the Contractor will begin digging and installing pipe at 31st between Bay and Haven: Concurrent with this work, the contractor will continue saw cutting on areas of Bay South of 18th Street. 
Traffic:
Traffic detours will be established along Bay South of 18th Street to avoid staged material located on the West shoulder and sawcut areas of the road. Expect 31st as well as areas of Bay to be local traffic only. Please obey all established traffic patterns. 
Scope/Timeline:
Timeline for Force Main Project

Contact Information:
Please refer all inquiries to bayaveforcemain@cmcmua.com
Phone Calls to Josh Palombo, Wastewater Program Manager, CMCMUA (609) 456-9026 