Active work:
Work continues from 31st between Bay and Haven and will turn North on Bay during the week of 9/30/19. The Contractor is expected to progress North at a pace of about one block per week. 

Traffic:
Bay Ave will be closed between 34th and 24th streets. Traffic detours will be established to divert motorists to West Ave. The picture below depicts the North and South traffic pattern to be followed. Please obey all established traffic patterns. 