Wastewater Force Main Replacement Project Bay Avenue, Ocean City Update #6 - Week of 10/7/19 through 10/11/19

Cape May County Municipal Utilities Authority

Wastewater Force Main Replacement Project

Bay Ave, Ocean City, NJ

Update #6- Week 10/7/19 through 10/11/19

Active work: 
As of the end of the day (Friday 10/4/19), the Contractor will have set the final chamber on 31st St, about 40' short of Bay Ave. All trenches on 31st Street will be backfilled and paved. On Monday 10/7/19, work will begin to turn north onto Bay Ave. It is expected that one crew will be working between 31st and 30th streets for the duration of the week.

Traffic:
Bay Ave will be closed between 34th and 24th streets. Traffic detours will be established to divert motorists to West Ave. The picture below depicts the North and South traffic pattern to be followed. Please obey all established traffic patterns.

traffic week 4.png

Scope/Timeline:

timeline week 4.png

Contact Information:
Please refer all inquiries to bayaveforcemain@cmcmua.com
Phone Calls to Josh Palombo, Wastewater Program Manager, CMCMUA (609) 456-9026 

For Prior Updates Click Here

More: Home News